Updated timeline of planning applications
29 November 2009
This is an outline of when facilities at Aldermaston have gone through the planning process
| FACILITY | TO PLANNING | FULL APPROVAL | COST |
| Orion laser | December 2003 | January 2006 | £183m |
| IT buildings | December 2004 | February 2005 | |
| Office buildings | December 2004 | February 2005 | |
| Gemini complex | October 2006 | January 2007 | £60-70m |
| Small scale components facility | September 2007 | November 2007 | |
| High Explosives Fabrication Facility | November 2007 | February 2008 | |
| Conventional Manufacturing Facility | June 2008 | August 2008 | |
| Warhead Assembly/Disassembly Facility | December 2008 | March 2009 | £30m |
| Enriched Uranium Facility | November 2009 | ||
| Hydrodynamics Facility Main | Mid 2010 | ||
| Systems Engineering Facility | Beyond 2010 | ||
| Small Scale Formulations | |||
| Chemical Processing | |||
| Emergency Response Capability Facility | |||
| Non Metallurgy and Material Science | |||
| High Performance Computer | |||
| New Office Accommodation Phase 3 |